PART I
Three Roundabouts
Drake/Maple
Now open to traffic
- Start Construction: May 2007; Finished Construction Sept 2007
Farmington/Maple
Now open to traffic
- Start Construction Aug 2007; Finished Construction Nov 2007
Farmington/14 Mile
- Start Construction Summer 2008; Finish Construction Fall 2008
PART II
Orchard Lake Road
Orchard Lake Road widening and reconstruction
Northwestern Highway intersection
Daly-Powers “connector”
Maple Road/Orchard Lake Road roundabout
14 Mile Road/Orchard Lake Road roundabout
Construction Start: Spring 2009 tentatively
(depending on necessary right of way acquisition)
Construction Finish: 2010
PART III
Three Roundabouts
Haggerty/Maple Road roundabout
Haggerty/14 Mile Road roundabout
Drake/14 Mile Road roundabout
Construction Start: To Be Determined